Green Tower — Bulevardi Gjergj Fishta
Site timelapse
Project facts
| Developer | Titan Konstruksion |
|---|---|
| Building contractor | Not on file |
| Architect | ARPA Project / Ark. Redi Pasko · Licence A.0207 |
| Structural engineer | Agim Seranaj · Licence K-0012/3 |
| Site supervisor | Right Click · Licence MK.4339 |
| Technical director | Not on file |
| Electrical engineer | Erjon Kokoshi · Licence E.1216/1 |
| Mechanical engineer | Dorian Koco · Licence M.1006/2 |
| Permit decision | Nr. Leje Ndërtimi Nr. 334/25, Aug. 20, 2024 |
| Stated works duration | 48 months (per permit — not a completion estimate) |
| Estimated completion | Aug. 20, 2028 — decision date + stated duration, not something the board or developer said outright. ~23 months remaining, estimate. |
| Floors | 18 |
| Last observed | Sept. 17, 2026 |